Dept. of Trans. PROGRESS Serial No. Contract No. 26-021-12-13 08-1J3004 PROGRESS PAYMENT VOUCHER %complete: %time: 80% 65% Location: Federal Project: 08-SBD-18-90.9/R96.6 ACNH-P018(65) Progress payment No. 011 Payment period ending: 01-20-26 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,652,626.00 530,777.29 2. a. Extra Work 210,872.84 34,156.84 b. Adustment Comp. -8,467.90 -32,360.84 3. Materials on Hand 356,060.14 10,990.50 4. Earned Subject to Retention 10,211,091.08 543,563.79 5. Mobilization 700,000.00 0.00 6. Total Work Completed 10,555,030.94 7. Deductions -1,935.48 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 10,909,155.60 543,563.79 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 543,563.79