Dept. of Trans. PROGRESS Serial No. Contract No. 26-051-10-19 08-1J3004 PROGRESS PAYMENT VOUCHER %complete: %time: 81% 71% Location: Federal Project: 08-SBD-18-90.9/R96.6 ACNH-P018(65) Progress payment No. 012 Payment period ending: 02-20-26 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,902,609.18 249,983.18 2. a. Extra Work 210,872.84 0.00 b. Adustment Comp. -8,467.90 0.00 3. Materials on Hand 325,847.14 -30,213.00 4. Earned Subject to Retention 10,430,861.26 219,770.18 5. Mobilization 700,000.00 0.00 6. Total Work Completed 10,805,014.12 7. Deductions -1,935.48 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,128,925.78 219,770.18 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 219,770.18