Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-107-15-14 08-1J3404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-10-9.6/R36.9 NONE 08-RIV-10-0.1/R156.4 Progress payment No. 011 Payment period ending: 02-28-19 PAVE-TECH INC 2231 LA MIRADA DRIVE VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,911,779.40 -30,803.67 2. a. Extra Work 90,235.87 87,735.87 b. Adustment Comp. -10,823.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 7,991,191.76 56,932.20 5. Mobilization 456,823.50 0.00 6. Total Work Completed 8,448,015.26 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 8,443,015.26 56,932.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 56,932.20