Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-149-07-35 08-1J3504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-15-0.0/52.3 NONE 08-SBD-15-0.1/186.2 Progress payment No. 009 Payment period ending: 03-26-19 CAL STRIPE INC 2040 E STEEL RD COLTON CA 92324 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,395,195.60 45,991.50 2. a. Extra Work 27,665.12 10,758.52 b. Adustment Comp. -51,451.42 -41,253.02 3. Materials on Hand 4. Earned Subject to Retention 18,371,409.30 15,497.00 5. Mobilization 2,250,000.00 0.00 6. Total Work Completed 20,621,409.30 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,621,409.30 15,497.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,497.00