Dept. of Trans. PROGRESS Serial No. Contract No. 20-057-08-20 08-1J3904 PROGRESS PAYMENT VOUCHER %complete: %time: 30% 40% Location: Federal Project: 08-SBD-210-R25.5/R25.5 NONE Progress payment No. 002 Payment period ending: 02-20-20 BEADOR CONSTRUCTION COMPANY 26320 LESTER CIR CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 151,061.50 144,311.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 151,061.50 144,311.50 5. Mobilization 69,384.11 69,384.11 6. Total Work Completed 220,445.61 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 214,445.61 207,695.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 207,695.61