Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-08-08 08-1J4704 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 83% Location: Federal Project: 08-RIV-10-R87.9 NONE 08-RIV-10-R91.0 Progress payment No. 008 Payment period ending: 07-15-25 GRIFFITH COMPANY 3050 E BIRCH ST BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,214,271.45 347,674.78 2. a. Extra Work 213,286.46 8,582.08 b. Adustment Comp. 26,008.65 0.00 3. Materials on Hand 4. Earned Subject to Retention 5,453,566.56 356,256.86 5. Mobilization 545,000.00 0.00 6. Total Work Completed 5,998,566.56 7. Deductions -5,000.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,993,566.56 361,256.86 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 361,256.86