Dept. of Trans. PROGRESS Serial No. Contract No. 22-028-10-15 08-1J4904 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 69% Location: Federal Project: 08-SBD-138-15.3/15.3 NONE Progress payment No. 005 Payment period ending: 01-20-22 STANCE CONSTRUCTION COMPANY 9070 IRVINE CENTER DR #220 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 392,738.50 77,192.50 2. a. Extra Work 16,560.00 16,560.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 409,298.50 93,752.50 5. Mobilization 6. Total Work Completed 409,298.50 7. Deductions -12,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 397,298.50 93,752.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 93,752.50