Dept. of Trans. PROGRESS Serial No. Contract No. 25-353-13-41 08-1J6104 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 35% Location: Federal Project: 08-RIV-215-40.5/42.7 ACIM-2151(256) Progress payment No. 007 Payment period ending: 12-20-25 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,657,090.75 2,452,188.90 2. a. Extra Work 73,935.86 14,118.99 b. Adustment Comp. 3. Materials on Hand 177,371.12 -33,274.54 4. Earned Subject to Retention 9,908,397.73 2,433,033.35 5. Mobilization 1,957,000.00 0.00 6. Total Work Completed 11,688,026.61 7. Deductions -18,000.00 -9,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,847,397.73 2,424,033.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,424,033.35