Dept. of Trans. PROGRESS Serial No. Contract No. 26-021-17-42 08-1J6104 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 38% Location: Federal Project: 08-RIV-215-40.5/42.7 ACIM-2151(256) Progress payment No. 008 Payment period ending: 01-20-26 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,671,612.70 1,014,521.95 2. a. Extra Work 130,714.22 56,778.36 b. Adustment Comp. 3. Materials on Hand 168,972.54 -8,398.58 4. Earned Subject to Retention 10,971,299.46 1,062,901.73 5. Mobilization 1,957,000.00 0.00 6. Total Work Completed 12,759,326.92 7. Deductions -18,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,910,299.46 1,062,901.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,062,901.73