Dept. of Trans. PROGRESS Serial No. Contract No. 26-051-09-41 08-1J6104 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 43% Location: Federal Project: 08-RIV-215-40.5/42.7 ACIM-2151(256) Progress payment No. 009 Payment period ending: 02-20-26 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 11,513,136.75 841,524.05 2. a. Extra Work 130,714.22 0.00 b. Adustment Comp. 3. Materials on Hand 116,988.83 -51,983.71 4. Earned Subject to Retention 11,760,839.80 789,540.34 5. Mobilization 2,060,000.00 103,000.00 6. Total Work Completed 13,703,850.97 7. Deductions -68,000.00 -50,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 13,752,839.80 842,540.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 842,540.34