Dept. of Trans. PROGRESS Serial No. Contract No. 24-019-14-18 08-1J6704 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 62% Location: Federal Project: 08-RIV-15-9.4/16.3 ACNH-155(168) Progress payment No. 007 Payment period ending: 01-20-24 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 928,231.84 390,137.41 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 12,488.23 12,488.23 4. Earned Subject to Retention 940,720.07 402,625.64 5. Mobilization 180,500.00 0.00 6. Total Work Completed 1,108,731.84 7. Deductions -11,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,110,220.07 402,625.64 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 402,625.64