Dept. of Trans. PROGRESS Serial No. Contract No. 25-199-08-47 08-1J7204 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 31% Location: Federal Project: 08-SBD-40-S0.0/S0.8 ACIM-401(92) 08-SBD-40-0.0/R15.0 Progress payment No. 004 Payment period ending: 07-20-25 SULLY-MILLER CONTRACTING CO 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 24,192,466.02 5,903,392.43 2. a. Extra Work 5,137.00 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 24,197,603.02 5,903,392.43 5. Mobilization 3,750,000.00 187,500.00 6. Total Work Completed 27,947,603.02 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 27,947,603.02 6,090,892.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,090,892.43