Dept. of Trans. PROGRESS Serial No. Contract No. 25-107-13-55 08-1J8404 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 8% Location: Federal Project: 08-VAR ACST-000C(557) Progress payment No. 001 Payment period ending: 04-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 904,670.00 904,670.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 46,408.26 46,408.26 4. Earned Subject to Retention 951,078.26 951,078.26 5. Mobilization 500,000.00 500,000.00 6. Total Work Completed 1,404,670.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,451,078.26 1,451,078.26 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,451,078.26