Dept. of Trans. PROGRESS Serial No. Contract No. 25-294-08-42 08-1J8404 PROGRESS PAYMENT VOUCHER %complete: %time: 53% 70% Location: Federal Project: 08-VAR ACST-000C(557) Progress payment No. 007 Payment period ending: 10-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,764,527.25 1,149,539.25 2. a. Extra Work 106,835.97 69,879.45 b. Adustment Comp. 3. Materials on Hand 0.00 -3,093.88 4. Earned Subject to Retention 5,871,363.22 1,216,324.82 5. Mobilization 950,000.00 0.00 6. Total Work Completed 6,821,363.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 6,821,363.22 1,216,324.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,216,324.82