Dept. of Trans. PROGRESS Serial No. Contract No. 25-233-08-26 08-1J8604 PROGRESS PAYMENT VOUCHER %complete: %time: 20% 36% Location: Federal Project: 08-VAR ACNH-X071(76) Progress payment No. 004 Payment period ending: 08-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,310,243.00 1,261,868.00 2. a. Extra Work 10,367.31 10,367.31 b. Adustment Comp. 3. Materials on Hand 1,795,609.00 -441,000.00 4. Earned Subject to Retention 4,116,219.31 831,235.31 5. Mobilization 475,000.00 0.00 6. Total Work Completed 2,795,610.31 7. Deductions -13,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,578,219.31 831,235.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 831,235.31