Dept. of Trans. PROGRESS Serial No. Contract No. 20-238-14-46 08-1K0204 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 36% Location: Federal Project: 08-SBD-40-R10.0/R154.6 NONE Progress payment No. 001 Payment period ending: 08-20-20 PAVE-TECH INC 2231 LA MIRADA DRIVE VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 610,315.03 610,315.03 2. a. Extra Work 300.00 300.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 610,615.03 610,615.03 5. Mobilization 75,000.00 75,000.00 6. Total Work Completed 685,615.03 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 685,615.03 685,615.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 685,615.03