Dept. of Trans. FINAL Serial No. Contract No. 19-067-11-37 08-1K1504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-10-6.0/8.7 NONE Progress payment No. 005 Payment period ending: 10-25-18 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 323,500.22 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 323,500.22 0.00 5. Mobilization 6. Total Work Completed 323,500.22 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 323,500.22 0.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 0.00