Dept. of Trans. PROGRESS Serial No. Contract No. 25-262-09-54 08-1K4004 PROGRESS PAYMENT VOUCHER %complete: %time: 39% 28% Location: Federal Project: 08-RIV-15-3.5/6.8 ACIM-155(175) Progress payment No. 005 Payment period ending: 09-20-25 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,068,058.25 2,597,383.33 2. a. Extra Work 85,296.76 29,642.06 b. Adustment Comp. 3. Materials on Hand 188,772.61 188,772.61 4. Earned Subject to Retention 9,342,127.62 2,815,798.00 5. Mobilization 2,850,000.00 0.00 6. Total Work Completed 12,003,355.01 7. Deductions -712,500.00 -712,500.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,479,627.62 2,103,298.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,103,298.00