Dept. of Trans. PROGRESS Serial No. Contract No. 26-023-12-24 08-1K4004 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 47% Location: Federal Project: 08-RIV-15-3.5/6.8 ACIM-155(175) Progress payment No. 010 Payment period ending: 01-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 15,527,729.58 1,112,369.67 2. a. Extra Work 164,776.55 12,100.85 b. Adustment Comp. -28,387.11 -29,901.11 3. Materials on Hand 172,201.69 -9,199.07 4. Earned Subject to Retention 15,836,320.71 1,085,370.34 5. Mobilization 3,000,000.00 150,000.00 6. Total Work Completed 18,664,119.02 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 18,836,320.71 1,235,370.34 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,235,370.34