Dept. of Trans. PROGRESS Serial No. Contract No. 26-079-14-15 08-1K4004 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 57% Location: Federal Project: 08-RIV-15-3.5/6.8 ACIM-155(175) Progress payment No. 012 Payment period ending: 03-20-26 BEADOR CONSTRUCTION COMPANY INC 2900 BRISTOL ST #D204 COSTA MESA CA 92626 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 19,452,114.05 1,462,008.44 2. a. Extra Work 210,321.14 38,139.27 b. Adustment Comp. 98,126.07 51,300.00 3. Materials on Hand 149,185.65 -17,359.19 4. Earned Subject to Retention 19,909,746.91 1,534,088.52 5. Mobilization 3,000,000.00 0.00 6. Total Work Completed 22,760,561.26 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,909,746.91 1,534,088.52 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,534,088.52