Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-075-12-48 08-1K7304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-RIV-60-R0.4/15.9 NONE 08-RIV-215-R28.0/42.6 Progress payment No. 007 Payment period ending: 12-03-21 J MCLOUGHLIN ENGINEERING CO INC 10641 FULTON CT RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,002,471.19 0.00 2. a. Extra Work 276,900.56 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,279,371.75 0.00 5. Mobilization 280,000.00 0.00 6. Total Work Completed 3,559,371.75 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,559,371.75 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00