Dept. of Trans. PROGRESS Serial No. Contract No. 21-172-08-54 08-1K7404 PROGRESS PAYMENT VOUCHER %complete: %time: 32% 11% Location: Federal Project: 08-RIV-15-3.0/29.1 NONE Progress payment No. 001 Payment period ending: 06-20-21 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 139,630.65 139,630.65 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 139,630.65 139,630.65 5. Mobilization 57,000.00 57,000.00 6. Total Work Completed 196,630.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 196,630.65 196,630.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 196,630.65