Dept. of Trans. PROGRESS Serial No. Contract No. 21-235-11-40 08-1K7404 PROGRESS PAYMENT VOUCHER %complete: %time: 89% 55% Location: Federal Project: 08-RIV-15-3.0/29.1 NONE Progress payment No. 003 Payment period ending: 08-20-21 O'DONNELL CONSTRUCTION, INC. 559 W. COVINA BLVD SAN DIMAS CA 91773 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 491,907.35 149,189.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 491,907.35 149,189.00 5. Mobilization 60,000.00 0.00 6. Total Work Completed 551,907.35 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 551,907.35 149,189.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 149,189.00