Dept. of Trans. PROGRESS Serial No. Contract No. 21-333-13-59 08-1K7604 PROGRESS PAYMENT VOUCHER %complete: %time: 59% 100% Location: Federal Project: 08-RIV-91-1.0/20.3 NONE Progress payment No. 005 Payment period ending: 11-20-21 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 732,807.19 76,473.75 2. a. Extra Work 4,467.94 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 737,275.13 76,473.75 5. Mobilization 106,000.00 5,300.00 6. Total Work Completed 843,275.13 7. Deductions -76,473.75 -56,473.75 8. a. Contract Retentions b. Unsatisfactory Retentions -16,226.60 -7,647.38 c. Reduction after 95% Comp. 9. Total pay to Contractor 750,574.78 17,652.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 17,652.62