Dept. of Trans. PROGRESS Serial No. Contract No. 22-173-07-39 08-1K7804 PROGRESS PAYMENT VOUCHER %complete: %time: 90% 96% Location: Federal Project: 08-SBD-259-1.1/1.2 SNHG-P259(2) Progress payment No. 007 Payment period ending: 06-20-22 FBD VANGUARD CONSTRUCTION INC 550 GREENVILLE RD LIVERMORE CA 94550 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 362,633.90 2,287.60 2. a. Extra Work 26,476.11 0.00 b. Adustment Comp. 13,975.64 0.00 3. Materials on Hand 4. Earned Subject to Retention 403,085.65 2,287.60 5. Mobilization 6. Total Work Completed 403,085.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 403,085.65 2,287.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 2,287.60