Dept. of Trans. PROGRESS Serial No. Contract No. 23-144-07-25 08-1K8514 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 82% Location: Federal Project: 08-VAR-15-41.3/52.0 NONE Progress payment No. 008 Payment period ending: 05-20-23 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 654,192.00 5,190.00 2. a. Extra Work 14,921.18 5,592.84 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 669,113.18 10,782.84 5. Mobilization 35,000.00 0.00 6. Total Work Completed 704,113.18 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 704,113.18 10,782.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,782.84