Dept. of Trans. PROGRESS Serial No. Contract No. 23-024-15-38 08-1L0804 PROGRESS PAYMENT VOUCHER %complete: %time: 23% 15% Location: Federal Project: 08-RIV-79-M32.3/M33.8 SNHG-P079(47) Progress payment No. 004 Payment period ending: 01-20-23 CHUMO CONSTRUCTION INC 14425 JOANBRIDGE ST BALDWIN PARK CA 917061747 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 456,065.32 31,895.44 2. a. Extra Work 12,499.19 1,983.22 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 468,564.51 33,878.66 5. Mobilization 217,500.00 0.00 6. Total Work Completed 686,064.51 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 676,064.51 23,878.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 23,878.66