Dept. of Trans. PROGRESS Serial No. Contract No. 19-261-15-58 08-1L2604 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 100% Location: Federal Project: 08-SBD-178-5.5/12.0 NONE Progress payment No. 001 Payment period ending: 09-20-19 SULLY-MILLER CONTRACTING CO. 135 S STATE COLLEGE BLVD #400 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work 402,143.04 402,143.04 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 402,143.04 402,143.04 5. Mobilization 6. Total Work Completed 402,143.04 7. Deductions -6,000.00 -6,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 396,143.04 396,143.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 396,143.04