Dept. of Trans. PROGRESS Serial No. Contract No. 22-115-12-51 08-1L3304 PROGRESS PAYMENT VOUCHER %complete: %time: 86% 82% Location: Federal Project: 08-SBD-10-16.0/20.1 SNHG-X071(74) Progress payment No. 002 Payment period ending: 04-20-22 STERNDAHL ENTERPRISES INC 11861 BRANFORD ST SUN VALLEY CA 91352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 672,460.10 222,588.45 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 672,460.10 222,588.45 5. Mobilization 10,000.00 0.00 6. Total Work Completed 682,460.10 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 682,460.10 222,588.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 222,588.45