Dept. of Trans. PROGRESS Serial No. Contract No. 25-294-09-50 08-1L5104 PROGRESS PAYMENT VOUCHER %complete: %time: 8% 25% Location: Federal Project: 08-SBD-15-15.9 NONE Progress payment No. 001 Payment period ending: 10-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 76,025.50 76,025.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 76,025.50 76,025.50 5. Mobilization 60,000.00 60,000.00 6. Total Work Completed 136,025.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 136,025.50 136,025.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 136,025.50