Dept. of Trans. PROGRESS Serial No. Contract No. 25-328-14-47 08-1L5104 PROGRESS PAYMENT VOUCHER %complete: %time: 54% 53% Location: Federal Project: 08-SBD-15-15.9 NONE Progress payment No. 002 Payment period ending: 11-20-25 PETERSON-CHASE GEN ENGINEERING CONSTRUCTION INC 16351 CONSTRUCTION CIR WEST IRVINE CA 92606-4414 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 794,933.88 718,908.38 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 794,933.88 718,908.38 5. Mobilization 114,000.00 54,000.00 6. Total Work Completed 908,933.88 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 908,933.88 772,908.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 772,908.38