Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-19-10 08-1L6404 PROGRESS PAYMENT VOUCHER %complete: %time: 4% 31% Location: Federal Project: 08-VAR SNHG-000C(545) Progress payment No. 001 Payment period ending: 06-20-23 BC RENTALS LLC DBA BC TRAFFIC SPECIALIST 13261 GARDEN GROVE BLVD GARDEN GROVE CA 92843 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,850.00 2,850.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 60,294.50 60,294.50 4. Earned Subject to Retention 63,144.50 63,144.50 5. Mobilization 37,500.00 37,500.00 6. Total Work Completed 40,350.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 100,644.50 100,644.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 100,644.50