Dept. of Trans. PROGRESS Serial No. Contract No. 23-205-20-39 08-1L6404 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 56% Location: Federal Project: 08-VAR SNHG-000C(545) Progress payment No. 002 Payment period ending: 07-20-23 BC RENTALS LLC DBA BC TRAFFIC SPECIALIST 13261 GARDEN GROVE BLVD GARDEN GROVE CA 92843 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 599,957.96 597,107.96 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 0.00 -60,294.50 4. Earned Subject to Retention 599,957.96 536,813.46 5. Mobilization 75,000.00 37,500.00 6. Total Work Completed 674,957.96 7. Deductions -4,000.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 670,957.96 570,313.46 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 570,313.46