Dept. of Trans. PROGRESS Serial No. Contract No. 21-300-07-21 08-1L6504 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 37% Location: Federal Project: 08-SBD-58-R11.0/R23.0 NONE 08-SBD-58-R31.0/R34.8 08-SBD-40-0.0/R15.9 Progress payment No. 003 Payment period ending: 10-20-21 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,234,440.10 784,339.43 2. a. Extra Work b. Adustment Comp. -6,140.45 -6,140.45 3. Materials on Hand 0.00 -28,560.00 4. Earned Subject to Retention 1,228,299.65 749,638.98 5. Mobilization 278,302.50 58,590.00 6. Total Work Completed 1,506,602.15 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,506,602.15 808,228.98 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 808,228.98