Dept. of Trans. SEMI-FINAL Serial No. Contract No. 22-158-09-21 08-1L6504 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 08-SBD-58-R11.0/R23.0 NONE 08-SBD-58-R31.0/R34.8 08-SBD-40-0.0/R15.9 Progress payment No. 009 Payment period ending: 03-16-22 FEC FUTURE CONTRACTORS AND ENGINEERS INC 184 TECHNOLOGY DRIVE #205 IRVINE CA 92618 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,391,313.40 0.00 2. a. Extra Work 143,779.94 0.00 b. Adustment Comp. 11,037.67 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,546,131.01 0.00 5. Mobilization 292,950.00 0.00 6. Total Work Completed 2,839,081.01 7. Deductions 0.00 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,839,081.01 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00