Dept. of Trans. PROGRESS Serial No. Contract No. 21-299-14-57 08-1L6804 PROGRESS PAYMENT VOUCHER %complete: %time: 31% 39% Location: Federal Project: 08-RIV-15-8.2/23.9 NONE 08-RIV-91-7.5/13.4 Progress payment No. 003 Payment period ending: 10-20-21 RV CONCRETE INC 605 E COMMERCIAL ST ANAHEIM CA 92801 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 968,568.54 791,587.29 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 968,568.54 791,587.29 5. Mobilization 248,900.00 117,900.00 6. Total Work Completed 1,217,468.54 7. Deductions -20,000.00 -20,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,197,468.54 889,487.29 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 889,487.29