Dept. of Trans. PROGRESS Serial No. Contract No. 23-167-21-30 08-1L7004 PROGRESS PAYMENT VOUCHER %complete: %time: 73% 42% Location: Federal Project: 08-VAR-10 NONE Progress payment No. 002 Payment period ending: 06-20-23 INTERNATIONAL LINE BUILDERS, INC. 3955 TEMESCAL CYN RD CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 639,471.58 363,580.64 2. a. Extra Work 2,425.01 1,938.86 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 641,896.59 365,519.50 5. Mobilization 44,980.00 2,249.00 6. Total Work Completed 686,876.59 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 686,876.59 367,768.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 367,768.50