Dept. of Trans. PROGRESS Serial No. Contract No. 24-085-07-43 08-1L7014 PROGRESS PAYMENT VOUCHER %complete: %time: 72% 57% Location: Federal Project: 08-VAR NONE Progress payment No. 004 Payment period ending: 03-20-24 KANAAN CONSTRUCTION INC 230 S IRWINDALE AVE AZUSA CA 91702 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 692,642.00 236,663.00 2. a. Extra Work 13,146.51 0.00 b. Adustment Comp. 3. Materials on Hand 55,000.00 -31,349.00 4. Earned Subject to Retention 760,788.51 205,314.00 5. Mobilization 100,000.00 0.00 6. Total Work Completed 805,788.51 7. Deductions -59,578.50 -59,578.50 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 801,210.01 145,735.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 145,735.50