Dept. of Trans. PROGRESS Serial No. Contract No. 21-356-11-33 08-1L7604 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 100% Location: Federal Project: 08-SBD-210 NONE Progress payment No. 006 Payment period ending: 12-20-21 ACCU CONSTRUCTION INC 2098 S GRAND AVE #A SANTA ANA CA 92705 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 585,649.50 52,537.00 2. a. Extra Work 91,980.00 91,980.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 677,629.50 144,517.00 5. Mobilization 10,000.00 0.00 6. Total Work Completed 687,629.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 687,629.50 144,517.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 144,517.00