Dept. of Trans. PROGRESS Serial No. Contract No. 26-202-15-01 08-1L8104 PROGRESS PAYMENT VOUCHER %complete: %time: 35% 31% Location: Federal Project: 08-RIV-15-33.9/52.3 ACIM-155(176) 08-SBD-15-0.0/61.3 Progress payment No. 003 Payment period ending: 07-20-26 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,806,571.32 872,310.69 2. a. Extra Work 47,077.31 47,077.31 b. Adustment Comp. 3. Materials on Hand 105,862.83 -146,457.97 4. Earned Subject to Retention 1,959,511.46 772,930.03 5. Mobilization 437,760.00 92,160.00 6. Total Work Completed 2,291,408.63 7. Deductions -200,000.00 -200,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,197,271.46 665,090.03 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 665,090.03