Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 22-347-09-11 08-1L9604 PROGRESS PAYMENT VOUCHER %complete: %time: 83% 23% Location: Federal Project: 08-SBD-999 NONE Progress payment No. 002 Payment period ending: 11-20-22 ALFARO COMMUNICATIONS CONSTRUCTION INC 15614 S. ATLANTIC AVENUE COMPTON CA 90221 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 110,681.50 81,183.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 110,681.50 81,183.00 5. Mobilization 6. Total Work Completed 110,681.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 110,681.50 81,183.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,183.00