Dept. of Trans. PROGRESS Serial No. Contract No. 23-325-11-14 08-1L9704 PROGRESS PAYMENT VOUCHER %complete: %time: 11% 7% Location: Federal Project: 08-SBD-210-R23.1/R24.7 NONE 08-SBD-259-1.0/1.5 Progress payment No. 002 Payment period ending: 11-20-23 DIVERSIFIED LANDSCAPE COMPANY 21730 BUNDY CANYON RD WILDOMAR CA 92595 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,389.40 63,544.40 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 100,389.40 63,544.40 5. Mobilization 43,000.00 43,000.00 6. Total Work Completed 143,389.40 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 143,389.40 106,544.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 106,544.40