Dept. of Trans. PROGRESS Serial No. Contract No. 23-025-08-15 08-1M0504 PROGRESS PAYMENT VOUCHER %complete: %time: 68% 100% Location: Federal Project: 08-RIV-15-23.9/33.4 NONE Progress payment No. 006 Payment period ending: 01-20-23 ALL AMERICAN ASPHALT PO BOX 2229 CORONA CA 92878-2229 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,121,640.97 35,004.16 2. a. Extra Work 4,788.00 4,788.00 b. Adustment Comp. -5,079.79 -5,079.79 3. Materials on Hand 4. Earned Subject to Retention 4,121,349.18 34,712.37 5. Mobilization 256,000.00 0.00 6. Total Work Completed 4,377,349.18 7. Deductions -13,000.00 -8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,364,349.18 26,712.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 26,712.37