Dept. of Trans. PROGRESS Serial No. Contract No. 24-143-09-51 08-1N0504 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 54% Location: Federal Project: 08-SBD-62-142.3/142.6 NONE Progress payment No. 003 Payment period ending: 05-20-24 BOWE CONTRACTORS INC 609 BAILEY CT TEHACHAPI CA 93561 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 751,378.18 298,688.57 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 751,378.18 298,688.57 5. Mobilization 158,412.50 0.00 6. Total Work Completed 909,790.68 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 909,790.68 298,688.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 298,688.57