Dept. of Trans. PROGRESS Serial No. Contract No. 26-112-12-41 08-1N1214 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 75% Location: Federal Project: 08-SBD-15-180.9/185.5 NONE Progress payment No. 004 Payment period ending: 04-20-26 FERREIRA CONSTRUCTION CO INC 10370 COMMERCE CENTER DR #B20 RANCHO CUCAMONGA CA 91730 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,039,612.35 5,250.00 2. a. Extra Work 232,000.00 232,000.00 b. Adustment Comp. 58,375.93 -11,050.00 3. Materials on Hand 522,782.00 0.00 4. Earned Subject to Retention 1,852,770.28 226,200.00 5. Mobilization 175,356.00 0.00 6. Total Work Completed 1,505,344.28 7. Deductions -8,247.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions -22,620.00 -22,620.00 c. Reduction after 95% Comp. 9. Total pay to Contractor 1,997,259.28 203,580.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 203,580.00