Dept. of Trans. PROGRESS Serial No. Contract No. 23-296-18-57 08-1N1404 PROGRESS PAYMENT VOUCHER %complete: %time: 21% 24% Location: Federal Project: 08-VAR NONE Progress payment No. 001 Payment period ending: 10-20-23 BC RENTALS LLC DBA BC TRAFFIC SPECIALIST 13261 GARDEN GROVE BLVD GARDEN GROVE CA 92843 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 195,323.52 195,323.52 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 195,323.52 195,323.52 5. Mobilization 183,750.00 183,750.00 6. Total Work Completed 379,073.52 7. Deductions -48,874.20 -48,874.20 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 330,199.32 330,199.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 330,199.32