Dept. of Trans. PROGRESS Serial No. Contract No. 24-018-18-53 08-1N2804 PROGRESS PAYMENT VOUCHER %complete: %time: 3% 13% Location: Federal Project: 08-RIV-15-16.5/17.6 SIMG-015(5) Progress payment No. 001 Payment period ending: 01-20-24 DANNY C HUBBS CONSTRUCTION INC 37306 VISTA VIEW DR YUCAIPA CA 92399 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 21,610.00 21,610.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 21,610.00 21,610.00 5. Mobilization 6. Total Work Completed 21,610.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 21,610.00 21,610.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,610.00