Dept. of Trans. PROGRESS Serial No. Contract No. 25-084-12-14 08-1N4704 PROGRESS PAYMENT VOUCHER %complete: %time: 7% 3% Location: Federal Project: 08-VAR NONE Progress payment No. 001 Payment period ending: 03-20-25 SELECT ELECTRIC INC 2790 BUSINESS PARK DR VISTA CA 92081 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 330,777.35 330,777.35 4. Earned Subject to Retention 330,777.35 330,777.35 5. Mobilization 191,658.00 191,658.00 6. Total Work Completed 191,658.00 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 522,435.35 522,435.35 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 522,435.35