Dept. of Trans. PROGRESS Serial No. Contract No. 25-169-08-11 08-1N4704 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 45% Location: Federal Project: 08-VAR NONE Progress payment No. 004 Payment period ending: 06-20-25 SELECT ELECTRIC INC 1700 E VIA BURTON ANAHEIM CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,300,488.10 384,379.12 2. a. Extra Work 58,299.93 19,389.05 b. Adustment Comp. -68,046.51 0.00 3. Materials on Hand 0.00 -50,000.00 4. Earned Subject to Retention 1,290,741.52 353,768.17 5. Mobilization 242,766.80 0.00 6. Total Work Completed 1,533,508.32 7. Deductions -5,000.00 -5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,528,508.32 348,768.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 348,768.17