Dept. of Trans. PROGRESS Serial No. Contract No. 25-202-09-45 08-1N4704 PROGRESS PAYMENT VOUCHER %complete: %time: 67% 58% Location: Federal Project: 08-VAR NONE Progress payment No. 005 Payment period ending: 07-20-25 SELECT ELECTRIC INC 1700 E VIA BURTON ANAHEIM CA 92806 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,573,388.50 272,900.40 2. a. Extra Work 124,701.26 66,401.33 b. Adustment Comp. -68,046.51 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,630,043.25 339,301.73 5. Mobilization 255,544.00 12,777.20 6. Total Work Completed 1,885,587.25 7. Deductions -15,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,870,587.25 342,078.93 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 342,078.93